Project Start Date: 3/14/07
Project Finish Date: 10/1/10
| ID | Name | Start_Date | Finish_Date | Percent_Complete |
|---|---|---|---|---|
| 1 | 2.1 DEVELOP EDUCATION AND OUTREACH PROGRAM | 8/15/07 | 1/25/08 | 37% |
| 2 | Review NEWSC Info and Education Plan | 8/15/07 | 9/11/07 | 100% |
| 3 | 2.1.7 Identify activities that may pose storm water contamination concern | 9/17/07 | 10/12/07 | 100% |
| 4 | Attend the Writing an Information and Education Plan workshop | 10/15/07 | 10/15/07 | 100% |
| 5 | Draft Education & Outreach Plan | 10/16/07 | 10/29/07 | 0% |
| 6 | Review Education & Outreach Plan | 10/31/07 | 11/13/07 | 0% |
| 7 | Revise Education & Outreach Plan | 11/14/07 | 12/11/07 | 0% |
| 8 | Final review of Education & Outreach Plan | 12/12/07 | 1/8/08 | 0% |
| 9 | Final revision of Education & Outreach Plan | 1/9/08 | 1/22/08 | 0% |
| 10 | 3.1A SUBMIT PROPOSED EDUCATION AND OUTREACH PROGRAM TO DNR | 1/25/08 | 1/25/08 | 0% |
| 11 | ||||
| 12 | 2.1 Public education and Outreach Program | 3/17/08 | 9/29/08 | 0% |
| 13 | 2.1.1 Promote detection and elmination of illicit discharges | 3/20/08 | 9/17/08 | 0% |
| 14 | 2.1.2 Inform/educate public about proper management of materials | 3/20/08 | 9/17/08 | 0% |
| 15 | 2,1,3 Promote beneficial onsite use of leaves and grass clippings | 3/18/08 | 9/17/08 | 0% |
| 16 | 2.1.4 Promote managerment of streambanks and shorelines | 3/17/08 | 9/12/08 | 0% |
| 17 | 2.1.5 Promote infiltration of residential storm water runoff | 3/17/08 | 9/12/08 | 0% |
| 18 | 2.1.6 Inform/educate on construction site erosion control practices | 3/17/08 | 9/12/08 | 0% |
| 19 | 2.1.8 Promote environmentally sensitive land development designs | 3/17/08 | 9/12/08 | 0% |
| 20 | 3.1.B IMPLEMENT PUBLIC EDUCATION AND OUTREACH PROGRAM | 9/29/08 | 9/29/08 | 0% |
| 21 | ||||
| 22 | 2.2 Public Involvement and Participation | 9/3/07 | 9/29/08 | 0% |
| 23 | 3.2.A SUBMIT PROPOSED PUBLIC INVOLVEMENT AND PARTICIPATION PROGRAM | 9/3/07 | 2/29/08 | 0% |
| 24 | 3.2.B IMPLEMENT PUBLIC INVOLVEMENT AND PARTICIPATION PROGRAM | 4/1/08 | 9/29/08 | 0% |
| 25 | ||||
| 26 | 2.3 Illicit Discharge detection and Elimination | 6/1/07 | 10/1/10 | 0% |
| 27 | 2.3.1 Ordinance to prevent illicit discharges (2.3.1.1 - 2.3.1.3) | 6/1/07 | 10/3/08 | 0% |
| 28 | 3.3.1.A SUBMIT PROPOSED DISCHARGE AND ELIMINATION ORDINANCE | 6/1/07 | 11/9/07 | 0% |
| 29 | 3.3.1.B IMPLEMENT ILLICIT DISCHARGE AND ELIMINATION ORDINANCE | 4/7/08 | 10/3/08 | 0% |
| 30 | ||||
| 31 | 3.3.3 COMPLETE INITIAL FIELD SCREENING OF DRY WEATHER DISCHARGES Actual end (9/30/09) | 6/1/07 | 9/30/09 | 0% |
| 32 | 2.3.2 Initial screening of all major outfalls during dry weather periods | 8/1/08 | 9/30/08 | 0% |
| 33 | 2.3.2.1 Visual observation | 8/1/08 | 9/30/08 | 0% |
| 34 | 2.3.2.2 Field analysis (2.3.2.2.1 - 2.3.2.2.2) | 8/1/08 | 9/30/08 | 0% |
| 35 | ||||
| 36 | 2.3.3 On-going dry weather screening (PHASE 2) | 7/2/07 | 10/1/10 | 0% |
| 37 | 3.3.4.A SUBMIT PROPOSED ON-GOING FIELD SCREENING PROGRAM (Actually ends 10/29/09) | 7/2/07 | 12/29/09 | 0% |
| 38 | 3.3.4.B IMPLEMENT ON-GOING FIELD SCREENING PROGRAM (Actually completes 10/1/10) | 10/1/10 | 10/1/10 | 0% |
| 39 | 11/8/07 | 11/8/07 | 0% | |
| 40 | 2.3.4 - 2.3.7 Procedures for responding to suspected illicit discharges (2.3.4.1 - 2.3.4.6) | 6/1/07 | 3/31/09 | 0% |
| 41 | 3.2.2.A SUBMIT PROPOSED ILLICIT DISCHARGE RESPONSE PRODEDURES | 6/1/07 | 10/1/08 | 0% |
| 42 | 3.2.2.B IMPLEMENT ILLICIT DISCHARGE RESPONSE PROCEDURES | 10/1/08 | 3/31/09 | 0% |
| 43 | 6/1/07 | 6/1/07 | 0% | |
| 44 | 2.4 Construction Site Pollutant Control | 6/1/07 | 10/3/08 | 0% |
| 45 | 2.4.1 Ordinance to reqire erosion and sediment control (2.4.1.1 - 2.4.1.6) | 6/1/07 | 10/3/08 | 0% |
| 46 | 3.4.1.A SUBMIT ORDINANCE FOR CONSTRUCTION SITE POLLUTANT CONTROL | 6/1/07 | 11/9/07 | 0% |
| 47 | 34.1.B ADOPT ORDINANCE FOR CONSTUCTING SITE POLLUTANT CONTROL | 4/7/08 | 10/3/08 | 0% |
| 48 | ||||
| 49 | 2.4.2 Procedures for construction site inspection (2.4.2.1 - 2.4.2.4) | 6/1/07 | 10/3/08 | 0% |
| 50 | 3.4.2.A SUBMIT PROPOSED CONSTRUCTION SITE INSPECTION & ENFORCEMENT PROCEDURES | 6/1/07 | 11/9/07 | 0% |
| 51 | 3.4.2.B IMPLEMENT CONSTRUCTION SITE INSPECTION & ENFORCEMENT PROCEDURES | 4/7/08 | 10/3/08 | 0% |
| 52 | ||||
| 53 | 2.4.3 Procedures for receipt of information from the public | 6/1/07 | 10/3/08 | 0% |
| 54 | ?.?.? SUBMIT PROCEDURES FOR RECEIPT OF INFORMATION FROM THE PUBLIC | 6/1/07 | 11/9/07 | 0% |
| 55 | ?.?.? IMPLEMENT PROCEDURES FOR RECIIPT OF INFORMATION FROM THE PUBLIC | 4/16/08 | 10/3/08 | 0% |
| 56 | ||||
| 57 | 2.5 Post-Construction storm Water Management | 6/1/07 | 10/3/08 | 0% |
| 58 | 2.5.1 Ordinance to regulate post-construction storm water discharges (2.5.1.1 -2.5.1.6) | 6/1/07 | 10/3/08 | 0% |
| 59 | 3.5.1.A SUBMIT PROPOSED POST-CONSTRUCTION STORM WATER MANAGEMENT ORDINANCE | 6/1/07 | 11/9/07 | 0% |
| 60 | 3.5.1.B IMPLEMENT POST-CONSTRUCTION STORM WATER MANAGEMENT ORDINANCE | 4/16/08 | 10/3/08 | 0% |
| 61 | ||||
| 62 | 2.5.2 Procedures for long-term maiuntenance of storm water management facilities | 6/1/07 | 10/3/08 | 0% |
| 63 | 3.5.2.A SUBMIT PROPOSED LONG-TERM MAINTENANCE PROCEDURES | 6/1/07 | 11/9/07 | 0% |
| 64 | 3.5.2.B IMPLEMENT LONG-TERM MAINTENANCE PROCEDURES | 4/16/08 | 10/3/08 | 0% |
| 65 | ||||
| 66 | DEVELOP ORDINANCES FOR PARA 2.3, 2.4, 2.5 ABOVE | 6/1/07 | 10/3/08 | 29% |
| 67 | Prepare draft ordinances | 6/1/07 | 6/14/07 | 100% |
| 68 | Customize draft ordinances to TR specs | 6/21/07 | 8/3/07 | 100% |
| 69 | Task Force Meeting & Review | 8/6/07 | 8/31/07 | 100% |
| 70 | Prepare draft/proposed ordinances | 8/28/07 | 10/8/07 | 100% |
| 71 | Public, Attorney,Staff, Task Force & City Council review | 10/4/07 | 10/4/07 | 100% |
| 72 | Brief council on project funding inplications | 11/5/07 | 11/5/07 | 100% |
| 73 | Revise ordinances | 11/6/07 | 11/6/07 | 0% |
| 74 | 2nd Public, Attorney,Staff, Task Force & City Council review | 11/2/07 | 11/2/07 | 0% |
| 75 | City Manager, submit proposed ordinances to DNR | 11/9/07 | 11/9/07 | 0% |
| 76 | Receive DNR comments on proposed ordinances | 11/16/07 | 4/16/08 | 0% |
| 77 | Revise ordinances TR | 4/17/08 | 4/30/08 | 0% |
| 78 | Public, Task Force & Council review and input | 4/28/08 | 5/23/08 | 0% |
| 79 | Final revisions of ordinances | 5/26/08 | 6/6/08 | 0% |
| 80 | Public Hearings | 6/5/08 | 7/2/08 | 0% |
| 81 | Council review & approval | 7/3/08 | 7/3/08 | 0% |
| 82 | Submit ordinances to DNR for approval | 7/10/08 | 7/10/08 | 0% |
| 83 | Implement ordinances | 7/14/08 | 10/3/08 | 0% |
| 84 | ||||
| 85 | 2.6 Pollution Prevention (2.6.1 - 2.6.9) | 1/7/08 | 3/27/08 | 0% |
| 86 | ||||
| 87 | 2.7 Storm Water Quality Management | 6/1/07 | 3/31/09 | 53% |
| 88 | 2.7.1.a 20% REDUCTION OF TOTAL SUSPENDED SOLIDS (Phase 1) | 3/3/08 | 9/26/08 | 0% |
| 89 | 2.7.1.b 40% REDUCTION OF TOTAL SUSPENDED SOLIDS (Phase 2 - Nov 2008 - Oct 2013) | 10/1/08 | 3/31/09 | 0% |
| 90 | ||||
| 91 | 3.7 COMPLETE EVAL OF FLOOD CONTROL STRUCTURES & ASSESSMENT OF COMPLIANCE - NOT APPLICABLE | 6/1/07 | 10/2/08 | 100% |
| 92 | 2.7.2 Evaluation of flood control facilities NOT APPLICABLE | 6/1/07 | 8/23/07 | 100% |
| 93 | ||||
| 94 | 2.7.3 Pollutant analysis using SLAMM | 6/4/07 | 3/26/08 | 35% |
| 95 | Accumulate data for SLAMM TR | 6/4/07 | 6/15/07 | 100% |
| 96 | Input inital data to SLAMM | 6/21/07 | 7/18/07 | 100% |
| 97 | Prepare final data for input to SLAMM | 7/12/07 | 7/24/07 | 100% |
| 98 | Input final data to SLAMM | 7/25/07 | 8/7/07 | 100% |
| 99 | Run SLAMM "no controlls" | 8/14/07 | 9/10/07 | 100% |
| 100 | Run SLAMM for current practices | 9/12/07 | 10/9/07 | 100% |
| 101 | Present initial SLAMM results to Council, Staff & Task Force | 10/16/07 | 10/16/07 | 0% |
| 102 | Develop 20% TSS solutions (BUDGET?) | 10/22/07 | 11/16/07 | 0% |
| 103 | Develop 40% TSS solutions (BUDGET?) | 11/19/07 | 2/8/08 | 0% |
| 104 | Request DNR & State legislative support (Bulkheads, Lake Bed Grants) | 12/7/07 | 3/26/08 | 0% |
| 105 | Revise solutions based on DNR & State responses | 12/3/07 | 12/3/07 | 0% |
| 106 | Entineering of 20% & 40% solutions | 12/3/07 | 12/3/07 | 0% |
| 107 | Contracting for 20% solutions | 12/3/07 | 12/3/07 | 0% |
| 108 | Award of contracts | 12/3/07 | 12/3/07 | 0% |
| 109 | 20% TSS reductions achieved | 12/3/07 | 12/3/07 | 0% |
| 110 | ||||
| 111 | 2.8 Storm Water System Map (2.8.1 -2.8 8) | 12/6/07 | 8/27/08 | 0% |
| 112 | Develop Storm Water System Map | 12/6/07 | 8/26/08 | 0% |
| 113 | 3.8 STORM WATER SYSTEM MAP | 8/27/08 | 8/27/08 | 0% |
| 114 | ||||
| 115 | 2.9 Annual Report (2.9.1 -2.9.5) | 3/14/08 | 5/8/08 | 0% |
| 116 | 3.10 ANNUAL REPORT (MAR 31 2009 & ANNUALLY THEREAFTER) | 3/31/09 | 3/31/09 | 0% |